Milestone 1 – Steps

February 2014 – December 2017 (gazette Feb 2018)
Objective: draft Zoning Design for Milestone 1 (15%) 

  1. Launch MSP Process
  2. MSP Governance Framework
  3. Stakeholder Groups and Terms of Reference
  4. Data catalogue
  5. Planning Tools and decision-support tools
  6. MSP Zoning Framework
  7. Stakeholder Consultations and Public Workshops
  8. Website
  9. Information brochure
  10. Analyse new data
  11. Develop draft zoning designs
    • develop options based on stakeholder recommendations
    • Run decision support tools
    • Examine outputs, feedback and discussion
    • Revise and iterate
  12. Allowable Activities Tables
  13. Management Considerations
  14. Proposal for Milestone 1 areas
  15. Approval from MSP stakeholder groups
  16. Submit Cabinet Memo for approval to prepare nomination file
  17. Cabinet approval to prepare nomination file
  18. Prepare and submit nomination file
  19. Approval from Ministry of Environment, Energy and Climate Change
  20. Public review, as per National Park and Nature Conservancy Act (NPNCA)
  21. Review public feedback
  22. Finalise Proposed Areas for Milestone 1
  23. Gazette areas for Milestone 1
  24. Workplan for Phase 2 – Milestone 2