Milestone 3 – Steps

January – February 2019
Objective: Data analysis, mapping, preparing for stakeholder consultations  

  1. Finalise Nomination File Process with MEECC
  2. Workplan for Milestone 3
  3. Data gathering and updates; analyse new data
  4. Review and incorporate comments from stakeholder consultations
  5. Begin climate change risk mapping
  6. Gazette and Designation Order signed for Milestone 2
  7. Update MSP Atlas maps

 March – April 2019
Objective: Stakeholder consultations – Inception Workshop Milestone 3

  1. Milestone 3 Inception Workshop to discuss and receive proposals for Milestone
  2. Executive Committee meeting
  3. Technical Working Group meeting
  4. Stakeholder consultations
  5. Public Information Workshops
  6. Review climate change risk mapping
  7. Discuss Allowable Activities Tables and Management Considerations
  8. Public information sessions on Mahe, Praslin and La Digue

May – June 2019
Objective: Revise MSP Zoning Design 4.3 and draft version 5.0 for Milestone 3

  1. Iterate and revise draft zoning design v5.0
  2. Revise draft allowable activities and management considerations based on stakeholder consultations
  3. Advance climate change risk mapping

July 2019
Objective: Stakeholder consultations – Review zoning design Milestone 3 areas  

  1. Executive Committee Meeting
  2. Steering Committee Meeting
  3. Stakeholder consultations
  4. Public Information Workshops
  5. Technical Working Group
  6. Steering Committee
  7. Executive Committee Meeting

 August – December 2019
Objective: Revisions and stakeholder consultations for Milestone 3 areas

  1. Executive Committee Meeting
  2. Steering Committee Meeting
  3. Stakeholder consultations
  4. Public Information Workshops
  5. Finalise climate change risk mapping
  6. Approval from Cabinet to submit Nomination File for 30% zoning design
  7. Prepare and submit Nomination File